Day of accomplishment!

Much progress was made today on the project. We had our meeting with Seamus at 9.00am and discussed what needed to be done for next week. We decided it would be best to get all the requirements done for the project.

Instead of dragging out this work over the period of a week we did 6 hours of work after our meeting with Seamus and accomplished the following:

  • All Use Cases were finished
  • All Use Case diagrams were done and included with the Use Cases
  • A Sequence diagram for the app was completed
  • The Android prototype we had was expanded upon
  • A wordpress site was setup on my server in order to have a website to add/edit islands:
           http://photofiltre-lx.org/islandadmin/
  • A secondary HTML/CSS website was made in order to have a backup option in case we were not happy with the wordpress solution.

Plans for during the week

I will be doing more work on the secondary website over the next few days.

Dean will be developing the PHP system for the website.

Sarah will be merging the documentation and organizing it into a single document.

Sunday, February 12, 2012

Progress this week

Over this week we had a team meeting on Monday to discuss and work on more Requirements documentation.

We then had a meeting Wednesday at 9.00am with our supervisor to show our progress. We came to the conclusion that we would need to do use cases for Friday.

After classes on Wednesday we set about doing those use cases. Seven use cases were created. We sent them via e-mail to our supervisor on Friday.

The next step is to develop a working prototype of our Android app so we can test our design ideas and set a foundation to build on.

Thursday, February 2, 2012

Meeting with Supervisor

Today we had a meeting with our supervisor (Seamus Lankford) and discussed our current work on requirements. We will take his advice onboard and move forward with the requirements.

We plan to do use cases on Monday at 13.00.

On Tuesday we will meet again to continue the work done on Monday.

A meeting will be held with Seamus on Wednesday at 9.00 to show our progress.

Wednesday, February 1, 2012

Third Meeting

The meeting took place at 1 pm on tuesday 31st and lasted 1 hour. It was delay from monday at the request of one of the members.

What was discussed during the meeting:
  • We evaluated our work for the previous week.
  • We choose to use the volere process as a templete.

After this we decided what each of us would have done for thursday (our first meeting with our supervisor).Sarah is going to merge all the requirements documents created by us from last week. I (Dean) am going to write up the non-functional requirements. Dylan is going to finish project constraints.